A3218 Lillie Road, London, Hammersmith And Fulham
11 July — 17 July Traffic control (multi-way signals)
Delays likely due to Streetworks
Network Operations Faults:Install / Replace Link Box: (Approx Depth 450mm):Nw London High Risk Link Box Replacement at A3218
Responsibility: UK Power Networks
EToN status: Planned work about to start
B317 North End Road, London, Hammersmith And Fulham
11 July — 12 July Contra-flow
Delays likely due to Streetworks
Replace 1 Jointbox Frame And Cover(S) (625mm X 625mm) In Carriageway at B317
Responsibility: BT
EToN status: Planned work about to start
A402 Goldhawk Road, London, Hammersmith And Fulham
10 July — 14 July Some carriageway incursion
Delays possible due to Streetworks
Boundary Box Remove In Footway. Our Intention Is To Complete Thepermanent Reinstatement In The Same Phase at A402
Responsibility: Thames Water
EToN status: Planned work about to start
A402 Goldhawk Road, London, Hammersmith And Fulham
10 July — 14 July Some carriageway incursion
Delays possible due to Streetworks
Locate And Excavate 1 Blockage In Existing Duct at A402
Responsibility: BT
EToN status: Planned work about to start

 

 

Information supplied by Roadworks.org

 

 