Roadworks in the Hammersmith Area

Where to expect traffic delays in the days ahead

 

Related Links

Roadworks in the Hammersmith Area

Live Travel News for Hammersmith

Participate
Sign up for our free weekly newsletter

Comment on this story on the
A219 Butterwick, London, Hammersmith And Fulham
26 October — 28 October Lane closure
Delays likely due to Streetworks
Excavation - Replacement Of Existing Telecommunications Mast. Day 1 Install New Ductwork With Pedestrian Manaement. Day 2 Swap Existing Telecomms Mast With New Mast Using Hiab, Lane Closure In Operation. Day 3 Complete Works And Reinstate Site at A219
Responsibility: T-Mobile (UK)Limited
EToN status: Planned work about to start
A219 Fulham Palace Road, London, Hammersmith And Fulham
26 October — 28 October Lane closure
Delays likely due to Streetworks
Lane 2 Closure Of Fulham Palace Road Northbound. Part Of The Hammersmith Flyover Drainage Works. at A219
Responsibility: Transport For London
EToN status: Planned work about to start
A219 Fulham Palace Road, London, Hammersmith And Fulham
26 October — 28 October Road closure
Delays likely due to Streetworks
Lane 2 Closure Of Fulham Palace Road Northbound. Part Of The Hammersmith Flyover Drainage Works. at A219
Responsibility: Transport For London
EToN status: Advanced planning
A219 Queen Caroline Street, London, Hammersmith And Fulham
26 October — 30 October Lane closure
Delays likely due to Streetworks
Disconnect 1 X 2" Pe Service From Main In Carriageway at A219
Responsibility: National Grid Gas Plc
EToN status: Planned work about to start
A315 King Street, London, Hammersmith And Fulham
26 October — 30 October Lane closure
Delays likely due to Streetworks
Disconnect 1 X 2" Pe Service From Main In Carriageway at A315
Responsibility: National Grid Gas Plc
EToN status: Planned work about to start
B408 Paddenswick Road, London, Hammersmith And Fulham
26 October — 13 November Traffic control (two-way signals)
Delays likely due to Streetworks
This Permit Is For Thames Water, Which Will Involve Carrying Out A 25mm Sewer Connection And 110mm Manhole To Existing 1500mm Trunk Sewer, Works In The Carriageway at B408
Responsibility: Thames Water
EToN status: Planned work about to start

 

 


Information supplied by Roadworks.org

 

October 26, 2015

Bookmark and Share