North End Road Roadworks Continue till Weekend

Stretch from Lillie Road till Bramber Road reopens on Saturday

Related links

Motorists Warned of Roadworks across Borough

Town Centre Parking Bays to Close throughout 2014

Flyover Repairs Cause Christmas Traffic Disruption

Councils Row over Proposed Putney Bridge Closure

Putney Bridge Could Be Closed for Six Months

Shepherd's Bush Road Undergoes Major Shake Up

Live Travel News in Hammersmith

Register for the Shepherd's Bush Newsletter

Get the Hammersmith newsletter

Register for the Fulham Newsletter

Essential road works in North End Road, at the junction of Lillie Road, afre continuing until the weekend after the council’s contractors came up against unforeseen engineering difficulties.

This means the road will stay closed between Lillie Road and Bramber Road until all drainage and carriageway resurfacing work finishes, which is now expected to be on Saturday March 15 at noon.

Hammersmith & Fulham Council’s cabinet member for transport and technical services Cllr Victoria Brocklebank-Fowler says: " Our contractors are doing everything they can to get the work done as quickly as possible, with extended working hours over the weekend and will be monitoring the site closely.

" We will also be checking the works via CCTV to make sure everything is being done to finish as soon as possible."

The work is to unblock and replace old gullies that will help drain away rain water and prevent flooding in the area.

For more information please contact Donna Kelly on 020 8753 3040 or Nicky Moodley on 020 8753 2402.

March 13, 2014