| A402 Goldhawk Road, London, Hammersmith And Fulham |
| 27 July — 28 July Traffic control (Stop/Go boards) |
Delays likely due to Streetworks
Sec 81 - Frame And Cover Repairs In C/W at A402 |
| Responsibility: Abovenet Communications UK Ltd |
| EToN status: Planned work about to start |
|
|
| B317 North End Road, London, Hammersmith And Fulham |
| 27 July — 31 July Lane closure |
Delays likely due to Streetworks
Network Operations Maintenance:Install / Replace Link Box: (Approx Depth 450mm):Lb No. 130499 - A - Replace A Very Poor Condition Link Box In The Footway. Until The Excavation On A Link Box Is Complete We Are Unaware On Totally What We May Find. If Service Cables Are Found That Could Be To Blocks Of Flats, Businesses Or Houses Then We Need To, By Law Give All Customers 5 Days Notice That Their Electric Supply Will Be Interrupted For Up To 8 Hours. at B317 |
| Responsibility: UK Power Networks |
| EToN status: Planned work about to start |
|
|
| A219 Butterwick, London, Hammersmith And Fulham |
| 28 July — 30 July Some carriageway incursion |
Delays possible due to Streetworks
Build Chamber And Lay Duct In Footway To Connect New Client at A219 |
| Responsibility: Virgin Media |
| EToN status: Planned work about to start |
|
|
| A315 Hammersmith Road, London, Hammersmith And Fulham |
| 28 July — 30 July Some carriageway incursion |
Delays possible due to Streetworks
Build Chamber And Lay Duct In Footway To Connect New Client at A315 |
| Responsibility: Virgin Media |
| EToN status: Planned work about to start |
|
|
| A315 Kensington High Street, London, Kensington And Chelsea |
| 27 July — 07 August Some carriageway incursion |
Delays possible due to Streetworks
Sewer Failure--Works Intended To Include First Time Permanent Reinstatement Within Same Phase at A315 |
| Responsibility: Thames Water |
| EToN status: Planned work about to start |
|
|
| A315 King Street, London, Hammersmith And Fulham |
| 27 July — 07 August Some carriageway incursion |
Delays possible due to Streetworks
Imga160061. Excavate And Replace 25m Of 150mm Di Gas Main With New125mmpe Pipe. Transfer Services To No 182, 184, 186, 188 Kingsstreet. at A315 |
| Responsibility: National Grid Gas Plc |
| EToN status: Planned work about to start |
|
|
| A3219 Munster Road, London, Hammersmith And Fulham |
| 27 July — 07 August Some carriageway incursion |
Delays possible due to Streetworks
Construct A New Manhole O/S 228 In The Carriageway To Install An Anti-Flooding Device To Prevent Internal Sewer Flooding To The Property. A Slip Trench Across The Footpath Is Required For An Electricity Cable Connection To The Property. at A3219 |
| Responsibility: Thames Water |
| EToN status: Planned work about to start |
|
|
| A3219 Munster Road, London, Hammersmith And Fulham |
| 27 July — 07 August Some carriageway incursion |
Delays possible due to Streetworks
Construct A New Manhole O/S 303 In The Footway & Carriageway To Install An Anti-Flooding Device To Prevent Internal Sewer Flooding To The Property. A Slip Trench Across The Footpath Is Required For An Electricity Cable Connection To The Property. at A3219 |
| Responsibility: Thames Water |
| EToN status: Planned work about to start |
|
|
| A3220 Addison Road, London, Kensington And Chelsea |
| 28 July — 29 July Some carriageway incursion |
Delays possible due to Streetworks
Maintenance - Replace - 2 Uneven Cut Slabs Caused By Tree Roots 1 600 1 750 Area 0.81m Sq. Partial Lane 1 Closure / Partial Fw Closure at A3220 |
| Responsibility: Transport For London |
| EToN status: Planned work about to start |
|
|
| A4 Talgarth Road, London, Hammersmith And Fulham |
| 27 July — 29 July Some carriageway incursion |
Delays possible due to Streetworks
Uneven Paving Pedestrian Signing Lighting And Guarding Only - No Carriageway Incursion Eb 0800 To 1630 at A4 |
| Responsibility: Transport For London |
| EToN status: Planned work about to start |
|
|
|
|
| B408 Dalling Road, London, Hammersmith And Fulham |
| 27 July — 07 August Some carriageway incursion |
Delays possible due to Streetworks
Imga160061. In Conjunction With Works Taking Place In King Street. at B408 |
| Responsibility: National Grid Gas Plc |
| EToN status: Planned work about to start |
|
|
|